File #: 26-703   
Type: CC - Approval of Change Order
File created: 7/27/2026 In control: City Council
On agenda: 8/10/2026 Final action:
Title: To approve an increase to the current awarded contract amount of $1,808,461 by $405,916 for a total contract amount of $2,214,377 for Sidewalk Improvements - Plano Parkway from Independence Parkway to Alma Drive, Project No. 6901, from A & C Construction, Inc. for the Engineering Department; and authorizing the City Manager to execute all necessary documents. (Contract No. 2021-0213-B; Change Order No. 7)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
header
Department: Engineering
Director: B. Caleb Thornhill, P.E., Director of Engineering
Agenda Item: Sidewalk Improvements - Plano Parkway from Independence Parkway to Alma Drive, Project No. 6901
Recommended Action: Approval of Change Order
end
Item Summary
title
To approve an increase to the current awarded contract amount of $1,808,461 by $405,916 for a total contract amount of $2,214,377 for Sidewalk Improvements - Plano Parkway from Independence Parkway to Alma Drive, Project No. 6901, from A & C Construction, Inc. for the Engineering Department; and authorizing the City Manager to execute all necessary documents. (Contract No. 2021-0213-B; Change Order No. 7)
body
Previous Action/Presentation
On April 26, 2021, City Council awarded RFB No. 2021-0213-B for Sidewalk Improvements - Plano Parkway from Independence Parkway to Alma Drive, Project No. 6901, to MSB Constructors, Inc. in the amount of $2,442,179.00.

On April 6, 2022, staff administratively approved Change Order No. 1 for an increase in the amount of $11,648.24.

On August 31, 2022, staff administratively approved Change Order No. 2 for an increase in the amount of $79,193.82 and amended contract time.

On November 14, 2022, City Council approved Change Order No. 3 for an increase in the amount of $154,617.66 and amended contract time.

On January 4, 2023, staff administratively approved Change Order No. 4 to amend the contract time.

On March 19, 2024, City Council awarded a tender agreement between the City of Plano and US Casualty and Surety Insurance Company and a Completion Contract in the amount of $1,920,000 between the City of Plano and A & C Construction, Inc.

On June 10, 2024, City Council approved Change Order No. 5 for a decrease in the amount of $194,173.70 and amended contract time.

On March 18, 2025, staff administratively approved Change Order No. 6 for an increase the amount of $82,634.70 and amended contract time.
Background
The Engineering Department recommends appr...