Legislation Details

File #: 26-610   
Type: CC - Approval of Change Order
File created: 7/7/2026 In control: City Council
On agenda: 7/27/2026 Final action: 7/27/2026
Title: To approve a decrease to the current awarded contract amount of $13,568,203 by $131,544.25 for a total contract amount of $13,436,658.75 for 050 - Tom Muehlenbeck Recreation Center - Renovation, Project No. FAC-F-7525, from Lee Lewis Construction, Inc. for the Engineering - Facilities Division; and authorizing the City Manager to execute all necessary documents. (Contract No. CMAR RFQ 2023-0316-B, Change Order No. 1)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

header

Department:                      Engineering

Director:  B. Caleb Thornhill, P.E., Director of Engineering

Agenda Item:  050 - Tom Muehlenbeck Recreation Center - Renovation, Project No. FAC-F-7525

Recommended Action:  Approval of Change Order

end

Item Summary

title

To approve a decrease to the current awarded contract amount of $13,568,203 by $131,544.25 for a total contract amount of $13,436,658.75 for 050 - Tom Muehlenbeck Recreation Center - Renovation, Project No. FAC-F-7525, from Lee Lewis Construction, Inc. for the Engineering - Facilities Division; and authorizing the City Manager to execute all necessary documents. (Contract No. CMAR RFQ 2023-0316-B, Change Order No. 1)

body

Background

The Engineering - Facilities Division recommends approval of Change Order No. 1 for the decrease in the construction contract with Lee Lewis Construction, Inc. in the amount of $131,544.25 for 050 - Tom Muehlenbeck Recreation Center - Renovation, Project No. FAC-F-7525.  This change does not amend the contract time from 434 calendar days.

 

Change Order No. 1 is a reconciliation of final project costs for contractual shared savings of project subcontractor buyout and unused contractor contingency.

 

If this change order is not approved, funds will remain allocated to the completed contract leaving them unavailable for utilization in other Tom Muehlenbeck Center Projects.

Financial Summary/Strategic Goals

This item approves a change in the contract with Lee Lewis Construction, Incfor construction services for the Tom Muehlenbeck Recreation Center - Renovation project.  The first change order, reducing the current contract by $131,544, will leave the balance of funds available to be utilized in other improvements to the facility.

 

Approval of this item will support the City's Strategic Plan Critical Success Factors of being an Excellent, Innovative, and Accountable City Government.