header
Department: Special Projects
Director: Peter Braster, Director of Special Projects
Agenda Item: Construction Manager-at-Risk for City of Plano Police Training Center, Project No. SP-F-00003
Recommended Action: Items for Individual Consideration
end
Item Summary
title
Consideration to approve RFQ No. 2026-0396-B for Construction Manager-at-Risk for City of Plano Police Training Center, Project No. SP-F-00003, for Special Projects to CORE Construction Services of Texas, Inc. in the amount of $42,000,000; and authorizing the City Manager to execute all necessary documents.
body
Background
Special Projects recommends award of the Construction Manager-at-Risk for City of Plano Police Training Center, Project No. SP-F-00003, in an amount not to exceed $42,000,000, inclusive of the pre-construction services fee of $42,000 and all general conditions. This action initiates the pre-construction phase and positions the City to begin construction in accordance with the adopted project schedule.
The Police Training Center project replaces the existing 21,904-square-foot Plano Police Training Facility at 4921 14th Street with a new facility of approximately 33,000 square feet, to be designed by Brinkley Sargent Wiginton Architects. The new facility includes cadet classrooms, an indoor tactical village, a gym and locker area, an Emergency Vehicle Operations Course (EVOC) classroom, and an expansion of the EVOC concrete pad. The project also includes demolition of the existing facility.
The City is using the Construction Manager at Risk (CMAR) delivery method authorized by Chapter 2269 of the Texas Government Code. Under this method, the construction manager provides pre-construction services during design, including constructability reviews, phasing analysis, long-lead procurement planning, and cost validation, and then serves as the general contractor during construction under a Guaranteed Maximum Price (GMP). Early contractor involvement is well suited to a ...
Click here for full text