File #: 26-930   
Type: CC - Approval of Change Order
File created: 10/9/2026 In control: City Council
On agenda: 11/9/2026 Final action:
Title: To approve an increase to the current awarded contract amount of $2,091,725 by $206,600 for a total contract amount of $2,298,325 for Arterial Concrete Repair Custer Road – SH 121 to Hedgcoxe Road, Project No. PW-S-00067, from R&A Legacy Construction LLC for the Public Works Department; and authorizing the City Manager to execute all necessary documents. (Contract No. 2026-0071-B; Change Order No. 1)
Attachments: 1. Agenda Item Memo, 2. Location Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
header
Department: Public Works
Director: Abby Owens, Director of Public Works
Agenda Item: An increase for Arterial Concrete Repair Custer Road – SH 121 to Hedgcoxe Road, Project No. PW-S-00067
Recommended Action: Approval of Change Order
end
Item Summary
title
To approve an increase to the current awarded contract amount of $2,091,725 by $206,600 for a total contract amount of $2,298,325 for Arterial Concrete Repair Custer Road – SH 121 to Hedgcoxe Road, Project No. PW-S-00067, from R&A Legacy Construction LLC for the Public Works Department; and authorizing the City Manager to execute all necessary documents. (Contract No. 2026-0071-B; Change Order No. 1)
body
Previous Action/Presentation
On February 9, 2026, City Council awarded RFB No. 2026-0071-B for Arterial Concrete Repair Custer Road – SH 121 to Hedgcoxe Road, Project No. PW-S-00067, to R&A Legacy Construction LLC in the amount of $2,091,725.
Background
Public Works recommends the approval of Change Order No. 1, increasing the current awarded contract amount of $2,091,725 by $206,600, for a total contract amount of $2,298,325 to R&A Legacy Construction LLC for the Arterial Concrete Repair Custer Road – SH 121 to Hedgcoxe Road, Project PW-S-00067.

This change order is for additional quantities of contract items that are necessary to complete arterial concrete repairs identified in the field by Public Works staff during construction. Additional repairs are required due to further deterioration of the subgrade and pavement, and drainage issues discovered during project progress that were not evident during inventory.

These repairs are necessary to ensure the street is repaired in preparation for the future asphalt overlay placement. Typically, estimates for concrete repairs are within 10% - 15% of the actual street repairs needed within the project limits. In this case, the estimate was about 10% lower than the actual repairs needed. This change order will not increase the per unit costs of the...