Title: To approve a decrease to the current awarded contract in the amount of $16,303,863 by $198,692 for a total contract amount of $16,105,171 for Sewer Improvements Dallas North Trunk, Phase 2 from S. J. Louis Construction of Texas, LTD. for the Engineering Department; and authorizing the City Manager to execute all necessary documents. (Contract No. 2025-0205-B; Change Order No. 7)
Attachments: 1. Agenda Item Memo, 2. Location Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

header

Department:                      Engineering

Director:  B. Caleb Thornhill, P.E., Director of Engineering

Agenda Item:  Approve a decrease in the amount of $198,692 for Sewer Improvements Dallas North Trunk Phase 2, Project No. 7467

Recommended Action:  Approval of Change Order

end

Item Summary

title

To approve a decrease to the current awarded contract in the amount of $16,303,863 by $198,692 for a total contract amount of $16,105,171 for Sewer Improvements Dallas North Trunk, Phase 2 from S. J. Louis Construction of Texas, LTD. for the Engineering Department; and authorizing the City Manager to execute all necessary documents. (Contract No. 2025-0205-B; Change Order No. 7)

body

Previous Action/Presentation

On May 13, 2025, City Council approved RFB No. 2025-0205-B for Sewer Improvements Dallas North Trunk, Phase 2, Project No. 7467 for the Engineering Department to S. J.  Louis Construction of Texas, LTD. in the amount of $16,139,315.03.

 

On November 17, 2025, staff administratively approved Change Order No. 1 for an increase in the amount of $36,701.67 associated with a waterline conflict.

 

On January 12, 2026, staff administratively approved Change Order No. 2 for an increase in the amount of $34,572.52 and 5 additional days due to unforeseen field conditions.

 

On March 31, 2026, staff administratively approved Change Order No. 3 for an increase in the amount of $79,904.90 to adjust manhole heights and to relocate a waterline conflict.

 

On April 22, 2026, staff administratively approved Change Order No. 4 for an increase in the amount of $5,031.00 associated with a waterline conflict.

 

On June 8, 2026, staff administratively approved Change Order No. 5 for an increase in the amount of $8,337.52 associated with a waterline conflict.

 

On August 20, 2026, staff administratively approved Change Order No. 6 with a 30-day contract extension and no cost change.

Background

The Engineering Department recommends approval of Change Order No. 7 for the decrease in the construction contract with S. J. Louis Construction of Texas, LTD. in the amount of $198,691.76 for the Sewer Improvements Dallas North Trunk, Phase 2.

 

Change Order No. 7 realigns a wastewater connection to avoid conflicts with unknown franchise utilities, reducing the amount of pipe, manholes, and related appurtenances. This change order also reflects a reduction in pier depths for wastewater aerial crossings, as stable rock was encountered at shallower depths than originally anticipated.

 

If this change order is not approved, unused funds from the original scope will not be returned to the City fund for other sewer infrastructure projects.

Financial Summary/Strategic Goals

This item approves a change in the contract with S. J. Louis Construction of Texas, LTD. for construction services for the Sewer Improvements Dallas North Trunk - Phase 2 project.  The seventh change order, reducing the current contract by $198,691, will leave the balance of funds available to be utilized in other sewer improvement projects.

 

Approval of this item will support the City’s Strategic Plan Critical Success Factors of being an Excellent, Innovative and Accountable City Government.