Title: Consideration to approve RFQ No. 2026-0152-B Construction Manager-At-Risk for the City of Plano Public Safety Campus for Special Projects to Swinerton Builders in the amount of $140,000,000; and authorizing the City Manager to execute all necessary documents. Approved
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

header

Department:                      Special Projects

Director:  Peter Braster, Director of Special Projects

Agenda Item:  Award RFQ 2026-0152-B Construction Manager-At-Risk for the City of Plano Public Safety Campus

Recommended Action:  Items for Individual Consideration

end

Item Summary

title

Consideration to approve RFQ No. 2026-0152-B Construction Manager-At-Risk for the City of Plano Public Safety Campus for Special Projects to Swinerton Builders in the amount of $140,000,000; and authorizing the City Manager to execute all necessary documents. Approved

body

Previous Action/Presentation

Include previous Council action, if applicable.

Background

Special Projects recommends award for the Construction Manager-At-Risk for the City of Plano Public Safety Campus to Swinerton Builders in an amount not to exceed $140,000,000, inclusive of the preconstruction services fee of $50,000 and all general conditions. This action initiates the pre-construction phase and positions the City to begin construction in accordance with the adopted project schedule.

 

The Plano Public Safety Campus is one of the most significant capital investments in the City's history. The project will consolidate essential public safety operations into a single, purpose-built campus located at the intersection of West Park Boulevard and Alma Drive. The campus will include the following facilities:

 

•                     New Police Headquarters

•                     911 Communications Center

•                     Central Utility Plant

•                     Parking Garage

•                     Fire Station No. 14

 

Together, these facilities will enhance emergency response capabilities, strengthen interdepartmental coordination, improve operational resilience, and position the City to meet the service demands of Together, these facilities will enhance emergency response capabilities, strengthen interdepartmental coordination, improve operational resilience, and position the City to meet the service demands of a growing community. The project represents a critical and time-sensitive step in replacing aging infrastructure that no longer meets the operational needs of the Plano Police and Fire Departments. growing community. The project represents a critical and time-sensitive step in replacing aging

infrastructure that no longer meets the operational needs of the Plano Police and Fire Departments.

Financial Summary/Strategic Goals

Funding for this item is available in the 2025-26 Police Headquarters Facility CIP and Public Safety Facilities CIP and is planned for future years in both funds as well. Construction services for the Plano Public Safety Campus project in the total amount of $140,000,000 will leave a combined balance of $17,151,551 for future expenditures on this project.

 

Approval of this item will support the City's Strategic Plan Critical Success Factors of being an Excellent, Innovative, and Accountable City Government with Safe, Vibrant Neighborhoods.