Department: Public Works
Director: Abby Owens, Director of Public Works
Agenda Item: Residential Concrete Pavement Repair Zone P3 South, Project No. PW-S-00061
Recommended Action: Approval of Change Order
end
Item Summary
title
To approve a decrease to the current awarded contract amount of $3,448,439 by $111,495 for a total contract amount of $3,336,944 for Residential Concrete Pavement Repair Zone P3 South, Project No. PW-S-00061, from Austin Raymond Construction, LLC dba Texas Civil Construction for the Public Works Department; and authorizing the City Manager to execute all necessary documents. (Contract No. 2024-0660-B; Change Order No. 2)
body
Previous Action/Presentation
On December 9, 2024, City Council awarded RFB 2024-0660-B for Residential Concrete Pavement Repair Zone P3 South, Project No. PW-S-00061, to Austin Raymond Construction, LLC dba Texas Civil Construction in the amount of $3,034,650.
On March 23, 2026, City Council approved Change Order No. 1 for an increase in the amount of $413,788.50.
Background
Public Works recommends the approval of Change Order No. 2, decreasing the current awarded amount of $3,448,439 by $111,495 for a total contract amount of $3,336,944 for Residential Concrete Pavement Repair Zone P3 South, Project PW-S-00061.
This change order is for a reduction in quantities of contract items that were not necessary to complete repairs in the project area. The remaining funds will be used on future residential projects.
If this change order is not approved at Council, the City will not be able to reallocate these funds to a future project.
Financial Summary/Strategic Goals
This item approves a change in the contract with Texas Civil for construction services for the Residential Concrete Pavement Repair Zone P3 South project. The second change order, reducing the current contract by $111,495, will leave the balance of funds available to be utilized in other street improvement projects.
Approval of this item will support the City's Strategic Plan Critical Success Factors of being an Excellent, Innovative, and Accountable City Government.
Attachments
Location Map