Legislation Details

File #: 26-1000   
Type: CC - Approval of Change Order
File created: 11/2/2026 In control: City Council
On agenda: 11/23/2026 Final action:
Title: To approve an increase to the current awarded contract amount of $3,932,529 by $223,221 for a total contract amount of $4,155,750 for Water Rehabilitation - Los Rios Addition and Ranch Estates, Project No. ENG-CMB-00005, from KIK Underground, LLC for the Engineering Department; and authorizing the City Manager to execute all necessary documents. (Contract No. 2025-0445-B; Change Order No. 2)
Attachments: 1. Agenda Item Memo, 2. Location Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

header

Department:                      Engineering

Director:  B. Caleb Thornhill, P.E., Director of Engineering

Agenda Item:  Change Order for Water Rehabilitation - Los Rios Addition and Ranch Estates, Project No. ENG-CMB-00005

Recommended Action:  Approval of Change Order

end

Item Summary

title

To approve an increase to the current awarded contract amount of $3,932,529 by $223,221 for a total contract amount of $4,155,750 for Water Rehabilitation - Los Rios Addition and Ranch Estates, Project No. ENG-CMB-00005, from KIK Underground, LLC for the Engineering Department; and authorizing the City Manager to execute all necessary documents. (Contract No. 2025-0445-B; Change Order No. 2)

body

Previous Action/Presentation

On September 16, 2025, City Council approved RFB No. 2025-0445-B for Water Rehabilitation - Los Rios Addition and Ranch Estates, Project No. ENG-CMB-00005, for the Engineering Department to KIK Underground, LLC in the amount of $3,892,579.79.

 

On May 28, 2026, staff administratively approved Change Order No. 1 for an increase in the amount of $39,948.95 for pavement restoration.

Background

The Engineering Department recommends approval of Change Order No. 2 for the increase in the construction contract with KIK Underground, LLC in the amount of $223,221.00 for Water Rehabilitation - Los Rios Addition and Ranch Estates, Project No. ENG-CMB-00005.

 

Change Order No. 2 reconciles final project quantities, which includes paving replacement for roadways found to be in poor condition along with associated sidewalks, barrier-free ramps, and storm inlet tops. Replacement of the deteriorating pavement is necessary to ensure a proper connection between the proposed pavement and the existing roadway. The change order also includes replacing a damaged storm sewer pipe found during water line installation across Country Club Drive and installing additional water service meters due to site conditions.

 

If this change order is not approved, the existing pavement will continue to deteriorate, which may lead to higher maintenance costs and negative traffic effects for residents.

 

Financial Summary/Strategic Goals

Funding for this item is available in the 2026-27 Street Improvement CIP and Water CIP. The second change order for Water Rehabilitation - Los Rios Addition and Ranch Estates, Project No. ENG-CMB-00005, in the total amount of $223,221, will leave a balance of $143,833 for future expenditures.

 

Approval of this item will support the City's Strategic Plan Critical Success Factor of being an Excellent, Innovative, and Accountable City Government.

Attachments

Location Map