Title: To approve an increase to the current awarded contract amount of $3,932,529 by $223,221 for a total contract amount of $4,155,750 for Water Rehabilitation - Los Rios Addition and Ranch Estates, Project No. ENG-CMB-00005, from KIK Underground, LLC for the Engineering Department; and authorizing the City Manager to execute all necessary documents. (Contract No. 2025-0445-B; Change Order No. 2)
Attachments: 1. Agenda Item Memo, 2. Location Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
header
Department: Engineering
Director: B. Caleb Thornhill, P.E., Director of Engineering
Agenda Item: Change Order for Water Rehabilitation - Los Rios Addition and Ranch Estates, Project No. ENG-CMB-00005
Recommended Action: Approval of Change Order
end
Item Summary
title
To approve an increase to the current awarded contract amount of $3,932,529 by $223,221 for a total contract amount of $4,155,750 for Water Rehabilitation - Los Rios Addition and Ranch Estates, Project No. ENG-CMB-00005, from KIK Underground, LLC for the Engineering Department; and authorizing the City Manager to execute all necessary documents. (Contract No. 2025-0445-B; Change Order No. 2)
body
Previous Action/Presentation
On September 16, 2025, City Council approved RFB No. 2025-0445-B for Water Rehabilitation - Los Rios Addition and Ranch Estates, Project No. ENG-CMB-00005, for the Engineering Department to KIK Underground, LLC in the amount of $3,892,579.79.

On May 28, 2026, staff administratively approved Change Order No. 1 for an increase in the amount of $39,948.95 for pavement restoration.
Background
The Engineering Department recommends approval of Change Order No. 2 for the increase in the construction contract with KIK Underground, LLC in the amount of $223,221.00 for Water Rehabilitation - Los Rios Addition and Ranch Estates, Project No. ENG-CMB-00005.

Change Order No. 2 reconciles final project quantities, which includes paving replacement for roadways found to be in poor condition along with associated sidewalks, barrier-free ramps, and storm inlet tops. Replacement of the deteriorating pavement is necessary to ensure a proper connection between the proposed pavement and the existing roadway. The change order also includes replacing a damaged storm sewer pipe found during water line installation across Country Club Drive and installing additional water service meters due to site conditions.

If this change order is not approved, the existing pavement will continue to ...