Legislation Details

File #: 26-998   
Type: CC - Approval of Change Order
File created: 10/30/2026 In control: City Council
On agenda: 11/23/2026 Final action:
Title: To approve a decrease to the current awarded contract in the amount of $16,303,863 by $198,692 for a total contract amount of $16,105,171 for Sewer Improvements Dallas North Trunk, Phase 2 from S. J. Louis Construction of Texas, LTD. for the Engineering Department; and authorizing the City Manager to execute all necessary documents. (Contract No. 2025-0205-B; Change Order No. 7)
Attachments: 1. Agenda Item Memo, 2. Location Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
header
Department: Engineering
Director: B. Caleb Thornhill, P.E., Director of Engineering
Agenda Item: Approve a decrease in the amount of $198,692 for Sewer Improvements Dallas North Trunk Phase 2, Project No. 7467
Recommended Action: Approval of Change Order
end
Item Summary
title
To approve a decrease to the current awarded contract in the amount of $16,303,863 by $198,692 for a total contract amount of $16,105,171 for Sewer Improvements Dallas North Trunk, Phase 2 from S. J. Louis Construction of Texas, LTD. for the Engineering Department; and authorizing the City Manager to execute all necessary documents. (Contract No. 2025-0205-B; Change Order No. 7)
body
Previous Action/Presentation
On May 13, 2025, City Council approved RFB No. 2025-0205-B for Sewer Improvements Dallas North Trunk, Phase 2, Project No. 7467 for the Engineering Department to S. J. Louis Construction of Texas, LTD. in the amount of $16,139,315.03.

On November 17, 2025, staff administratively approved Change Order No. 1 for an increase in the amount of $36,701.67 associated with a waterline conflict.

On January 12, 2026, staff administratively approved Change Order No. 2 for an increase in the amount of $34,572.52 and 5 additional days due to unforeseen field conditions.

On March 31, 2026, staff administratively approved Change Order No. 3 for an increase in the amount of $79,904.90 to adjust manhole heights and to relocate a waterline conflict.

On April 22, 2026, staff administratively approved Change Order No. 4 for an increase in the amount of $5,031.00 associated with a waterline conflict.

On June 8, 2026, staff administratively approved Change Order No. 5 for an increase in the amount of $8,337.52 associated with a waterline conflict.

On August 20, 2026, staff administratively approved Change Order No. 6 with a 30-day contract extension and no cost change.
Background
The Engineering Department recommends approval of Change Order No. 7 for the decrease in the constr...