header
Department: Engineering
Director: B. Caleb Thornhill, P.E., Director of Engineering
Agenda Item: Approve an increase in the amount of $711,337 for Pecan Hollow Golf Course Erosion Control for Holes 6 and 7, Project No. ENG-D-7419.1
Recommended Action: Approval of Change Order
end
Item Summary
title
To approve an increase to the current awarded contract amount of $3,347,634 by $711,337 for a total contract amount of $4,058,971 for Pecan Hollow Golf Course Erosion Control for Holes 6 and 7, Project No. ENG-D-7419.1, from Cardinal Strategies Construction Services, LLC for the Engineering Department; and authorizing the City Manager to execute all necessary documents. (Contract No. 2025-0366-B;
Change Order No. 1) Approved
body
Previous Action/Presentation
On September 8, 2025, City Council approved RFB No. 2025-0366-B for Pecan Hollow Golf Course Erosion Control for Holes 6 and 7, Project No. ENG-D-7419.1, for the Engineering Department to Cardinal Strategies Construction Services, LLC in the amount $3,347,634.
Background
The Engineering Department recommends approval of Change Order No. 1 for the increase in the construction contract with Cardinal Strategies Construction Services, LLC in the amount of $711,337 for the Pecan Hollow Golf Course Erosion Control for Holes 6 and 7.
During excavation, unforeseen soil and groundwater conditions along the streambank required additional geotechnical investigation and resulted in changes to the retaining wall foundation design. Change Order No. 1 covers the scope of work required to construct the revised foundation in response to the challenging soil conditions. The revised work includes deeper excavation, added foundation material, special shoring
support and continuous dewatering.
This change order also includes the installation of filter fabric for backfill, irrigation repairs from relocating the adjacent golf cart path, and a cost reduction for turf reinforcement mat due to material change.
If this cha...
Click here for full text